Purchase Reporting Request For Cashflow

Posted 2 days ago by Nathan Thorneycroft

Post a topic
N
Nathan Thorneycroft

When running projects we include/budget for spares/warranties to be ordered in the cashflow of the project.
We need this to report back  against the project cashflow.
example:
Project 1234 has 10 items @ $10.00 each that need to be purchased for the job directly. The project billings and cashflow allow for 1@ $10.00 spare item to be purchased and go to our stock holdings
An advanced PO is raised to purchase 10 items allocated to the project cost and 1 spare to inventory
The project reports as spend as $100.00 and $10.00 to stock however the budget of the project is for all 11 items $110.00 
For reporting back we need to identify both so that we can account for the  spend inline with the projects cashflow.

i created a custom field on the PO line "budget project cost" to try and create custom reports but the custom field does not go through to the reports section